Our energy and sustainability team advised the University on all matters relating to the installation of a wind turbine on their site. Pre-installation considerations included noise, the visual impact, air traffic control, grid connection, feed-in contract, selection of turbine, project financing, maintenance, warranties and insurance. AA Projects further managed the construction phase, erecting the turbine with a 30m rotor diameter calculated to provide payback within 5 years.